8 Piping installation
In this chapter
8.1 Preparing refrigerant piping................................................................................................................................................... 64
8.1.1 Refrigerant piping requirements ........................................................................................................................... 64
8.1.2 Refrigerant piping insulation.................................................................................................................................. 65
8.2 Preparing water piping ........................................................................................................................................................... 65
8.2.1 Water circuit requirements ................................................................................................................................... 65
8.2.2 Formula to calculate the expansion vessel pre-pressure...................................................................................... 68
8.2.3 To check the water volume and flow rate............................................................................................................. 68
8.2.4 Changing the pre-pressure of the expansion vessel ............................................................................................. 70
8.2.5 To check the water volume: Examples .................................................................................................................. 71
8.3 Connecting the refrigerant piping.......................................................................................................................................... 72
8.3.1 About connecting the refrigerant piping............................................................................................................... 72
8.3.2 Precautions when connecting the refrigerant piping............................................................................................ 72
8.3.3 Guidelines when connecting the refrigerant piping.............................................................................................. 73
8.3.4 Pipe bending guidelines ......................................................................................................................................... 74
8.3.5 To flare the pipe end.............................................................................................................................................. 74
8.3.6 To braze the pipe end ............................................................................................................................................ 75
8.3.7 Using the stop valve and service port.................................................................................................................... 75
8.3.8 To connect the refrigerant piping to the outdoor unit ......................................................................................... 77
8.3.9 To connect the refrigerant piping to the indoor unit............................................................................................ 77
8.4 Checking the refrigerant piping.............................................................................................................................................. 78
8.4.1 About checking the refrigerant piping................................................................................................................... 78
8.4.2 Precautions when checking the refrigerant piping ............................................................................................... 78
8.4.3 To check for leaks................................................................................................................................................... 79
8.4.4 To perform vacuum drying .................................................................................................................................... 79
8.4.5 To insulate the refrigerant piping .......................................................................................................................... 80
8.5 Charging refrigerant ............................................................................................................................................................... 81
8.5.1 About charging refrigerant .................................................................................................................................... 81
8.5.2 Precautions when charging refrigerant ................................................................................................................. 82
8.5.3 To determine the additional refrigerant amount.................................................................................................. 82
8.5.4 To determine the complete recharge amount...................................................................................................... 82
8.5.5 To charge additional refrigerant............................................................................................................................ 82
8.5.6 To fix the fluorinated greenhouse gases label....................................................................................................... 83
8.6 Connecting water piping ........................................................................................................................................................ 83
8.6.1 About connecting the water piping ....................................................................................................................... 83
8.6.2 Precautions when connecting the water piping.................................................................................................... 84
8.6.3 To connect the water piping.................................................................................................................................. 84
8.6.4 To connect the recirculation piping....................................................................................................................... 86
8.6.5 To fill the water circuit ........................................................................................................................................... 86
8.6.6 To fill the domestic hot water tank........................................................................................................................ 86
8.6.7 To insulate the water piping .................................................................................................................................. 87
8.1 Preparing refrigerant piping
8.1.1 Refrigerant piping requirements
INFORMATION
Also read the precautions and requirements in the "1 General safety
precautions"[46].
▪ Piping material: Phosphoric acid deoxidised seamless copper.
▪ Piping diameter:
Liquid piping Ø6.4mm (1/4")
Gas piping Ø15.9mm (5/8")
▪ Piping temper grade and thickness: