EasyManua.ls Logo

Daikin Enfinity VFC - Piping

Daikin Enfinity VFC
44 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
unit installation
IM 930-6 EnnityVerticalWaterSourceHeatPumps 10 www.DaikinApplied.com
Piping
1. Allunitsshouldbeconnectedtosupplyandreturn
pipinginatwo-pipereversereturnconguration.A
reversereturnsystemisinherentlyself-balancing
andrequiresonlytrimbalancingwheremultiple
quantitiesofunitswithdifferentowandpressuredrop
characteristicsexistinthesameloop.Checkforproper
waterbalancebymeasuringdifferentialtemperature
readingacrossthewaterconnections.Forproper
waterow,thedifferentialtemperatureshouldbe12°F
to14°F(5°Cto8°C)forunitsincoolingmode.
Adirectreturnsystemmayalsowork,butproperwater
owbalancingismoredifculttoachieveandmaintain.
2. Thepipingcanbesteel,copperorPVC.
Note: If using PVC (schedule-40) construction grade
pipe or better, use the manufacturers recom-
mended high temperature adhesive. With PVC
piping the appropriate number of hanger brackets
must be used to help prevent sagging.
3. Supplyandreturnrunoutsusuallyjointheunitviashort
lengthsofhighpressureexiblehosewhicharesound
attenuatorsforbothunitoperatingnoiseandhydraulic
pumpingnoise.Oneendofthehoseshouldhave
aswivelttingtofacilitateremovalforservice.Hard
pipingalsocanbebroughtdirectlytotheunit.This
optionisnotrecommendedsincenovibrationornoise
attenuationcanbeaccomplished.Thehardpiping
musthaveunionstofacilitateunitremoval.SeeFigure
8,Figure9,andFigure10fortypicalpipingdetails.
Figure 8: Typical Vertical Unit Piping
4. Someexiblehosethreadedttingsaresuppliedwith
sealantcompound.Ifnot,applyTeontapeforatightseal.
5. Supplyandreturnshutoffvalvesarerequiredat
eachunit.Thereturnvalveisusedforbalancingand
shouldhavea“memorystop”sothatitcanalways
beclosedoffbutcanonlybereopenedtotheproper
positionfortheowrequired.
6. Donotconnectanyunittothesupplyandreturnpiping
untilthewatersystemhasbeencleanedandushed
completely.Afterthecleaningandushinghastaken
place,theinitialconnectionshouldhaveallvalveswide
openinpreparationforwatersystemushing(see
"Cleaning&FlushingWaterSystem"onpage8).
7. Condensatepipingcanbesteel,copperorPVC.
Eachunitincludesacondensateconnection.
8. Unitsareinternallytrapped.
9. Donotlocateanypointinthedrainsystemabove
thedrainconnectionofanyunit.
10. Automaticowcontrolleddevicesmustnotbe
installedpriortosystemcleaningandushing.
11. Ahighpointofthepipingsystemmustbevented.
12. Checklocalcodefortheneedfordielectricttings.
Note: Do not over-torque ttings. The maximum torque
without damage to ttings is 30 foot pounds. If a
torque wrench is not available, use as a rule of
thumb, nger-tight plus one quarter turn.
Figure 9: Typical Vertical Installation and Unit Piping
1 SupplyAirDucting
2 AcousticalThermalLining(10ft.)
3 LineVoltage-7/8"(22mm)Hole
4 LowVoltage-7/8"(22mm)Hole
5 FlexibleDuctCollar
6 LouveredDoorforReturnAir
7 CondensateDrainConnection
8 FlexibleReturnHosewithFlowController/BallValve(3/4"FPT)
9 FlexibleSupplyHosewithY-Strainer/BallValve(3/4"FPT)
10 AccessPaneltoController
11 LEDAnnunciatorStatusLights
12 VibrationIsolationPad

Table of Contents

Related product manuals