Pre-Test Run Checks ESIE98–06A
4–4 Part 4 – Commissioning and Test Run
3
1
4
5
1.2 General Checks
Checklist A checklist of general checks is given below:
Check if …
1 there is external damage.
2 the unit is well supported and/or if the foundation is properly done.
3 the unit should be installed horizontally with a deviation of maximum 1°.
4 anti-vibration pads are required.
5 there is a drain possibility for the condensed water. (Only for EUWY5-30HB/C)
6 it is necessary to place a heatertape inside the drain system to prevent ice accumulation and
possible drain blockage during wintertime.
7 no metal dust or burrs remain after grinding or drilling in the metal construction parts during
the installation. This facilitates the rust process and thus shortens the unit’s lifetime.
8 the operator has received the operation manual.
9 the installer has received the installation manual.
10 the air volume over the coil is adequate; no blockage (from paper, plastic,...) or air short cir-
cuit due to wrong positioning.