EasyManuals Logo

Danfoss DSH Series Application Guide

Danfoss DSH Series
74 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #62 background imageLoading...
Page #62 background image
For the initial charge, the compressor must not run.
Charge refrigerant as close as possible to the nominal system charge.
This initial charging operation must be done in liquid phase between the condenser outlet and the lter drier.
If needed, a complement of charge can be done before evaporator, in liquid phase while compressor is running by
slowly throttling liquid in.
Never bypass safety low pressure switch.
For more detailed information see “Recommended refrigerant system charging practice“ AP000086421422.
Dielectric strength and insulation resistance tests
Several tests have been performed on each compressor at the factory between each phase and ground.
Dielectric strength test is done with a high potential voltage (hi-pot) of 2Un +1000V AC at least, and leakage
current must be less than 5 mA.
Insulation resistance is measured with a 500 V DC megohm tester and must be higher than 1 megohm.
Recommendations:
Additional dielectric test is not recommended as it may reduce motor lifetime. Nevertheless, if such as test is
necessary, it must be performed at a lower voltage.
Insulation resistance test can be done.
The presence of refrigerant around the motor windings will result in lower resistance values to ground and higher
leakage current readings. Such readings do not indicate a faulty compressor. To prevent this, the system can be
rst operated briey to distribute refrigerant.
Do not use a megohm meter nor apply power to the compressor while it is under vacuum as this may cause
internal damage.
Commissioning
Preliminary check
Check electrical power supply:
Phase order: Reverse rotation is obvious if the compressor do not build up pressure and sound level is abnormal
high. For DSH090-184 compressors equipped with internal reverse vent valve which can protect compressor
without damage within duration below 24h. For more details refer to section Phase sequence and reverse rotation
protection.
For DSH240 to DSH600 compressors equipped with an electronic module, reverse rotation will be automatically
detected. For more details refer to section Motor protection.
Voltage and voltage unbalance within tolerance: For more details refer to section Motor voltage.
Initial start-up
Crankcase heaters must be energized at least 6 hours in advance to remove refrigerant.
A quicker start-up is possible by “jogging” the compressor to evacuate refrigerant. Start the compressor for 1
second, then wait for 1 to 2 minutes. After 3 or 4 jogs the compressor can be started. This operation must be
repeated for each compressor individually.
System monitoring
The system must be monitored after initial startup for a minimum of 60 minutes to ensure proper operating
characteristics such as:
Correct superheat and subcooling.
Current draw of individual compressors within acceptable values (max operating current).
No abnormal vibrations and noise.
Correct oil level.
Scroll compressors, DSH090 to DSH600 | Application
© Danfoss | Climate Solutions | 2022.10 AB288965961751en-001402 | 62

Table of Contents

Other manuals for Danfoss DSH Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Danfoss DSH Series and is the answer not in the manual?

Danfoss DSH Series Specifications

General IconGeneral
BrandDanfoss
ModelDSH Series
CategoryAir Compressor
LanguageEnglish

Related product manuals