36 Eaton 93E UPS (20–30 kVA, 208/220V) Installation and Operation Manual 164000301—Rev 04
Figure 15. Power Terminal Cover Top Installation
Power Terminal Cover
Left Side Installed
Power Terminal Cover
Right Side Installed
Power Terminal Cover
Top Installed
NOTE Do not install the Power Terminal Cover Left and/or Right Side covers if wiring adjacent ancillary cabinets
(such as an EBC or IAC) using the power terminal base wiring channel.
Back
44..1111 IInnssttaalllliinngg IInntteerrffaaccee WWiirriinngg aanndd CCoonnnneeccttiioonnss
44..1111..11 IInnssttaalllliinngg BBuuiillddiinngg AAllaarrmm WWiirriinngg aanndd CCoonnnneeccttiioonnss
To install wiring:
1. Verify the UPS system is turned off and all power sources are removed. See
Chapter 7 UPS Operating Instructions for shutdown instructions.
2. To locate the appropriate terminals and review the wiring and termination requirements, see paragraph
3.2.3 UPS System Interface Wiring Preparation, Table 11, Figure 16, Figure 17, and Figure 18.
UPS System Installation