Prepare the EBM Cabinet
NOTE 1 The external battery cabinets are the same dimensions as the UPS cabinets. Refer to
the ”2.1 Preparing for Installation ” section for unpacking and cabinet setup.
NOTE 2 If you are installing multiple EBM(s) upstream to the UPS, repeat the setup as described
in this section.
1. Open the carton containing the external battery cabinet cable assembly and position it in the desired
location next to the UPS.
2. If you are rack-mounting the EBM cabinet, refer to the UPS rack-mount installation procedure (see
2.6 Rack-Mount Installation ). If not, proceed to the next step.
3. Install the anchor brackets to the floor if applicable (see 2.5 Anchor Bracket Installation ).