The following is a typical program and timetable for an installation project, once the
initial order has been received:
1. Project Meeting
Installer and user to be present; system specifications, schematic diagram and
proposed circuit drawing to be available. CF2000 Installation & Commissioning Guide
to be provided.
2. Equipment Fix
Typically 2 week's notice is required for equipment to be delivered. Cable to be
installed and bases/back boxes to be fitted. Then fire sensors, call points, alarm
sounders and interface units can installed.
3. Address Schedule
Schedule of sensor locations to be completed by installer and returned to enable
System programming.
4. Auto Learn
Fire panel panels to be installed and terminated. System to be powered up by
installer and auto learn mode activated (see Auto Learn section). System to be tested
and verified by installer, prior to final commissioning.
5. Final Commissioning
Minimum 2 weeks notice is required from receipt of Address Schedule and
Commission request form for an Eaton Fire Systems Service Engineer to attend
site to implement/oversee the final commissioning procedures (see Commissioning
section), in conjunction with the installer.