Installation
3.10 Commissioning the installation
After you have installed the T-Station, use the following procedure to test the system.
1. Make sure that all the electrical connections are secure.
2. Switch on the electrical supply and your exhaust-extraction system (if available).
3. To operate the system press the START/STOP key. Check that the equipment operates as described in
Section 3.9.
4. Check that the turbo pump reaches normal speed. If the pump inlet is valved or capped off, it should take
approximately 100 - 150 seconds for the turbo to reach normal speed. If you have attached a vacuum chamber to
the pump inlet, this time may take longer.
5. To turn OFF the system, press the START/STOP key followed by the ENTER key to confirm. Check that the
equipment closes down as described in Section 3.9.
For full operational details and how to navigate using the front panel control key pad refer to Section 4.3.