05/2019 - Art. Nr. 4200 1043 1803F8
D = see technical data
D1 = see technical data
DF = combustion chamber diameter
T1:
T = standard muffle depth
(option : extensions: see technical data)
Please note for reverse flow boilers:
For reverse flow boilers, dimension T1 is only
a recommended value. Depending on the type
of boiler, the combustion head must project at
least beyond the reversal gap by the
dimension below.
N/EKEVO 6/7 G-E - 50mm
N/EKEVO 6/7 G-EU2/G-EU2N/G-EU3/G-EF3
- 120mm
N
/
EKEVO 8/9 G-E/G-EU2/G-EU2N/G-EU3
- 120mm
T1 (mm)
N/EKEVO 6-9 G-EU2, G-EF3,
G-EU3, G-EU2N
>150… 300
N/EKEVO 6/7 G-E > 70… 200
N/EKEVO 8/9 G-E >150… 300
Installation
Boiler lining for G-E, G-EU2, G-EU2N, G-EU3, G-EF3 burner
Boiler lining
The burner lining must be installed at a
right angle to the burner tube. Possible
trimming work (bevelling, rounding) as
required for reverse boilers, for example,
should done at a diameter not below
70% of the combustion chamber
diameter. The space between the flame
tube of the burner and the boiler lining
should be lined with heat resistant
material, such as Cerafelt.
This space must not be lined with
brickwork
N6/N7 G-E / EKEVO 6/EKEVO 7 G-E
N6/N7 G-EF3 / EKEVO 6/EKEVO 7 G-EF3
N/EKEVO 6-9 G-EU2/G-EU2N/G-EU3
N/EKEVO 8-9 G-E
N/EKEVO 6-9 G-EU2/G-EU2N/G-EU3
N/EKEVO 8-9 G-E

Table of Contents

Related product manuals