Installing rails
Begin at the bottom of the cabinet space to install the rails.
All rails must be aligned level, front to back and with the companion rail, left to right.
Installing the DPE rails
The DPE rails should be installed first, at the bottom of the cabinet. The left adjustable
rail has a connector protruding from the front which goes through a hole in the front
channel of the cabinet and will connect to light the bezel.
Refer to Figure 3 on page 20 while performing the procedure that follows.
Procedure
1. Insert the adjustable 3U rail slide and seat both alignment pins into the rear channel
of your cabinet.
2. Extend the rail and align the front of the rails and ensure the connector extends
through a hole in the front channel.
3. Insert two retention screws in the two holes indicated in the front of each rail.
4. Insert two retention screws in the back of each rail.
Assemble components in your cabinet