Prothermo NMT81 Installation
Endress+Hauser 33
5.12.1 Top anchor method
Insert a temperature probe or a WB probe into a fixed pipe and secure it with a top anchor.
In NMS5, NMS7, NMS8x, and NMT81, both can be installed in one fixed pipe or gauge
pole.
150 (5.91)
1
2
3
4
5
6
7
8
9
20 (0.79)
300 (11.81)
500 - 1000
(19.69 - 39.37)
a
500
(19.69)
100 - 150
(3.94 - 5.90)
b
400
(15.75)
!18.2 (0.72)
!42 (1.65)
!27.2 (1.07)
A0042758
27 Top anchor method. Unit of measurement mm (in)
a Distance between the base plate and the bottom element
b Distance between the base plate and the WB probe
1 Converter (electrical compartment)
2 Flange
3 Top element
4 Temperature probe (without WB probe)
5 Stilling well hole
6 Temperature probe (with WB probe)
7 Base plate/datum plate
8 Tension wire
9 Top anchor
For the detailed installation procedure of top anchor, → 27