Commissioning Prothermo NMT81
64 Endress+Hauser
9.4 Guidance
Guidance contains three items: Commissioning, Calibration, and Import/Export; however
this section only describes Commissioning and Import / Export. We recommend that
calibration be performed by E+H service personnel, and the procedures are therefore not
listed in the operating instructions.
9.4.1 Commissioning
Commissioning means to perform the initial settings for measurement. When the DTM is
opened for the first time, commissioning of NMT81 will be required.
Commissioning procedure
1. Navigate to: Home → Guidance → Commissioning → Start
A0044587
55 Initial screen of commissioning
1 Home button
2 Operation menu: Guidance
3 Start button
2. Confirm that the device tag, name and serial number are correct, and select [Next].
A0044588
56 Device identification screen