IQ7+ and I Q7A Installation and Operation Manual - India
16 © 2023 Enphase Energy Inc. All rights reserved. August 2023
USM-00002-1.0
Step 5: Manage the cabling
A. Use cable clips or tie wraps to attach the cable to the racking. Make sure there is 1.8 m or less
between cable clips or tie wraps.
B. Dress any excess cabling in loops to avoid contacting the roof. Do not form loops smaller than 12 cm
in diameter.
WARNING: Tripping Hazard. Loose cables can become a tripping hazard. Dress the IQ Cable to
minimize this potential.
Step 6: Connect the microinverters
A. Connect the microinverter. Listen for a click as the connectors engage.
B. Cover any unused connectors with IQ Sealing Caps. Listen for a click as the connectors engage.
WARNING: Risk of electric shock. Risk of fire. Install sealing caps on all unused AC connectors, as
these connectors become live when the system is energized. Sealing caps are required for
protection against moisture ingress.
NOTE: If you need to remove a sealing cap, you must use the IQ Disconnect Tool. See Disconnect
a microinverter in this manual.