V10k automatic 4. Installation
17
EN
A’O-ring
BLower seat
C Socket and spring
4.7 Remove and mount the cover
1 Hold the cover at both sides, press your
thumb on the manometer and pull away
the cover at both sides at the same time.
1 Slide the cover over the T-shape rails (A)
of the body.
2 Press left and right until the cover is level
with the manometer and locked.
4.8 Preparation
Chlorination plants should be checked by a
specialist for condition according to the rules
before being taken into operation. Especially
the chlorine parts of the plant must be che-
cked for leaks.
When all the connections have been made,
the following pre-start checks must be carried
out before the plant can be taken into opera-
tion.
4.8.1 Check for water leaks
1 Close the regulating knob of the positio-
ner by hand or by the control.
2 Ensure that the gas cylinder or drum val-
ves are closed.
3 Open the stop valve at the point of appli-
cation.
4 Open the stop valve and the solenoid
valve in the water supply.
5 If installed start the booster pump.
6 Adjust the injector inlet pressure so that
the operation vacuum of 200 mbar is
displayed at the pressure gauge of the
V10k.
7 Check the water supply and the chlorine
solution line for leaks. Repair if necessary.