5. Operation V10k automatic
24
EN
5.7 Maintenance and inspection plan
* Maintenance level 1 can be performed by the operator/operating personnel.
Maintenance level 2 must be performed by specialist technicians trained by Evoqua or the
Evoqua customer service technicians.
Any work over and above this may only be performed subject to prior consultation with Evoqua
customer service.
Interval level Work to beperformed resources o.k. not o.k. remedied
daily 1
• Visual check for function
and leaks
weekly 1
• Check the chlorine lines for
leaks
• Check the function of the
system
monthly 1
• Clean the strainer in the
operation water line.
• Check the water level in
the syphon of the sink
every 3 months 1
• Check the auxiliary valves
for smooth operation,
replace if necessary
every 6 months 1
• Check the gas monitoring
system, replace the elec-
trolyte
1 • Check the system for leaks
yearly 2
• Maintenance of the sys-
tem, replace the gaskets
2-yearly 2 • Replace the copper pipes
3-yearly 2 • Replace the auxiliary valves
5-yearly 2
• Replace the pressure gau-
ges of the vacuum control
valves