Hardware Installation Manual for FJD 3D Excavator Guidance System
21
Copyright © FJ Dynamics Technology Co., Ltd. All Rights Reserved.
5.2 Power-on and Startup
5.2.1 Inspection before Power-on
1. Check that the power supply is connected correctly.
2. Check that the power supply voltage is satisfactory.
5.2.2 Inspection after Power-on
1. After power-on, please check if the power indicator of control terminal turns on.
2. After pressing the switch of control terminal, please check if control terminal program can be
started normally.
5.3 Specification Commissioning
Please refer to the Software Instruction Manual for FJD 3D Excavator Guidance System attached to the
machine for details of the parameter Commissioning.