Argus E25 MOD II - Operating Instructions
cated that this type of transport is
not possible.
Installing and connecting
the unit
ATTENTION!
The unit may only be installed,
removed, maintained and con-
nected by authorised persons.
Please contact the manufactur-
er if it is not possible to comply
with these conditions.
Contact the manufacturer if you
need help with the installation,
connections or commissioning
of the unit.
Preparing for installation
Take the unit out of its transport
packing.
Check the unit for transport damage.
If you find transport damage, contact
the manufacturer.
As delivered, the connections may be
closed with plugs.
Remove the plugs before installation.
Keep the plugs and packing materi-
als in a safe place for subsequent
use.
DANGER
When working on equipment
and components carrying elec-
tric voltage, or on pipework, very
serious injuries or death can be
caused by electric shock, burns,
high pressure in the system, or
poisoning.
➢ Make sure there are no hot
or hazardous media in the
pipelines.
➢ Make sure that all electric
power supplies to the unit
and connecting leads are
voltage-free.
➢ Make sure the plant is
switched off and secured
against unauthorised
switching back on.
➢ Make sure the unit and
pipelines have cooled so
that they are no more than
hand warm.
➢ Make sure that all electrical
connecting leads have ade-
quate insulation.
➢ Wear suitable protective
clothing and, when neces-
sary, use suitable protective
equipment.
For more information about suitable
protective clothing and protective
equipment, see the safety data sheet
for the medium being handled.
Make sure that all electric connec-
tions are voltage-free.
Empty the pipelines (when installing
the unit with ball valves / ball valve
combinations).