USER INSTRUCTIONSUSER INSTRUCTIONS
DMX/DMXD/DMXH/DMXDH centrifugalDMX/DMXD/DMXH/DMXDH centrifugal
pumpspumps
InstallationInstallation
OperationOperation
MaintenanceMaintenance
Multistage, single/double suction, horizontally split voluteMultistage, single/double suction, horizontally split volute
type centrifugal pumpstype centrifugal pumps
PCN = 71569282 10/09 (E)PCN = 71569282 10/09 (E)
BALL/BALL CONFIGURATIONBALL/BALL CONFIGURATION
These instructions must be read prior to installing,These instructions must be read prior to installing,
operating, using and maintaining the operating, using and maintaining the
equipment.equipment.
Question and Answer IconNeed help?

Do you have a question about the Flowserve DMX and is the answer not in the manual?

Flowserve DMX Specifications

General IconGeneral
BrandFlowserve
ModelDMX
CategoryWater Pump
LanguageEnglish

Summary

Introduction and Safety

General

General information and essential instructions for operating the pump safely and correctly.

CE marking and approvals

Details regarding CE marking directives and approvals applicable to the equipment.

Disclaimer

Information disclaimer concerning the manual's completeness and accuracy.

Copyright

Copyright notice for the user instructions manual.

Duty conditions

Guidelines for selecting the pump based on specific application duty conditions.

Safety

Comprehensive safety guidelines, including hazard warnings and personal protective equipment recommendations.

Warning labels

Explanation of safety symbols, warning labels, and their critical meanings for safe operation.

Specific machine performance

Information on accessing specific machine performance data and customer data sheets.

Noise level

Guidance on noise exposure, measurement, and estimated noise levels for pumps.

Installation

Grouting

Procedures and specifications for proper foundation grouting using various materials.

Initial alignment

Detailed steps and methods for achieving and verifying shaft and coupling alignment.

Pre-startup checks

Essential pre-operational checks including oil rings, piping, and general readiness.

Electrical connections

Guidelines for making safe and compliant electrical connections by qualified personnel.

Protection systems

Recommended protection systems for pumps in hazardous areas or handling hazardous liquids.

Commissioning, Start-up, Operation and Shutdown

Precommissioning procedure

Critical steps and checks required before the initial commissioning of the pump.

Initial start up procedure

Step-by-step guide for the safe and correct initial start-up of the pump unit.

Running or operation

Procedures and precautions for operating the pump safely and efficiently.

Stopping and shutdown

Instructions for safely stopping and performing shutdown procedures for the pump.

Hydraulic, mechanical and electrical duty

Factors influencing pump performance under different hydraulic, mechanical, and electrical conditions.

Maintenance

Dismantling the rotor

Detailed procedure for safely dismantling the pump rotor assembly.

Heating impellers for removal

Specific instructions and precautions for heating impellers during removal.

Examination of parts

Guidelines for inspecting and examining pump components after dismantling.

Inspection and renewal of parts

Detailed steps for inspecting parts for wear and determining renewal needs.

Assembly of pump and seal

Procedures for reassembling the pump, including bearings and sealing systems.

Bearing installation

Correct methods and precautions for installing ball bearings onto the shaft.