Figure 4: P-installation
These items are required:
• Guide bars
• Guide bar bracket for attaching the guide equipment to the access frame or to the
upper part of the sump
• Level regulators or other control equipment for start, stop, and alarm
• Cable holder for holding the cable and regulating the height of the level regulators
• Access frame (with covers) to which the upper guide bar bracket and cable holder can
be attached
• Discharge connection for connecting the pump to the discharge line
The discharge connection has a flange which fits the pump casing flange and a
bracket for attaching the guide equipment.
• Fasteners for the discharge connection
• Anchor bolts
1. Run a cable between the sump and the stator and monitoring equipment.
Make sure that the cable is neither sharply bent, nor pinched.
2. Install the access frame:
a) Place the access frame in position and align it horizontally.
b) Grout the frame in place.
3. Grout the anchor bolts in place.
Be careful when you align and position the discharge connection in relation to the
access frame.
4. Place the discharge connection in position, and tighten the nuts.
5. Install the guide bars:
a) Secure the guide bars in the bracket.
b) Check that the guide bars are placed vertically. Use a level or a plumb line.
6. Connect the discharge pipe to the discharge connection.
7. Prepare for the level regulator:
a) Bolt the cable holder to the access frame.
b) Attach the level regulator cable to the cable holder and adjust the height of the
level regulator.
c) Protect bolts and nuts with a corrosion-preventive compound.
Installation
Flygt 3202 Installation, Operation, and Maintenance Manual 19