Operating the System
Froling GmbH, Industriestraße 12, 4710 Grieskirchen, AUSTRIA Page 27
www.froling.com B0600008_US
3.3 Heat up the boiler
3.3.1 Prepare for Fueling
Open Insulation Door
Operating mode "Door open" will
be shown at the Graphic Display
of Boiler Control System
The Induced Draft Fan must
start automatically - you will hear
the noise
Cautiously open Fuel Loading Chamber Door, keeping face away from
opening
Check the amount of combustion residues within the Filling chamber
If level of ashes is not too high (i.e. you can see both upper rows
of air holes within the Cladding Plates), continue with fueling
If level of ashes is too high, refer to chapter 5.2.2 "Weekly
Maintenance" and remove the ashes before fueling
Check for combustion residues within the Flame Slot and remove all
of them