Care, maintenance and disposal
Under normal operating conditions the power source requires only a minimum of care
and maintenance. However, it is vital to observe some important points to ensure the
welding system remains in a usable condition for many years.
- Check mains plug, mains cable, welding torch, interconnecting hosepack and
grounding (earthing) connection for damage
- Check whether the all-round clearance of 0.5 m (1 ft 8 in.) is kept to ensure that the
cooling air can easily flow and escape.
NOTE! Air inlets and outlets must never be covered, not even partially.
- Clean air filter
- Dismantle device side panels and clean inside of device with dry reduced com-
pressed air
NOTE! Risk of damage to electronic components. Do not bring air nozzle too
close to electronic components.
- If a lot of dust has accumulated, clean the cooling air ducts.
Dispose of in accordance with the applicable national and local regulations.
WARNING! An electric shock can be fatal. Before opening the device
- Turn the mains switch to the „O“ position
- Unplug the device from the mains
- Put up an easy-to-understand warning sign to stop anybody inadvertently
switching it back on again
- Using a suitable measuring instrument, check to make sure that electri-
cally charged components (e.g. capacitors) have discharged
General
Safety
At every start-up
Every 2 months
Every 6 months
Disposal
WARNING! Operating the equipment incorrectly can cause serious injury and
damage. The following activities must only be carried out by trained and
qualified personnel. Pay particular attention to the „Safety rules“ section.