9–12 PQM POWER QUALITY METER – INSTRUCTION MANUAL
COMMISSIONING CHAPTER 9: COMMISSIONING
S5 TESTING
TEST RELAYS AND LEDS
OPERATION TEST
CURRENT/VOLTAGE SIMULATION
SIMULATION
SIMULATION ENABLED FOR min.
PHASE A CURRENT A
PHASE B CURRENT A
PHASE C CURRENT A
NEUTRAL CURRENT A
Vax VOLTAGE V
Vbx VOLTAGE V
Vcx VOLTAGE V
PHASE ANGLE °
ANALOG OUTPUTS SIMULATION
SIMULATION
SIMULATION ENABLED FOR min.
ANALOG OUTPUT 1 %
ANALOG OUTPUT 2 %
ANALOG OUTPUT 3 %
ANALOG OUTPUT 4 %
ANALOG INPUT SIMULATION
SIMULATION
SIMULATION ENABLED FOR min.
ANALOG INPUT mA
•SWITCH INPUTS SIMULATION
SIMULATION
SIMULATION ENABLED FOR min.
SWITCH INPUT A
SWITCH INPUT B
SWITCH INPUT C
SWITCH INPUT D
Table 9–1: PQM Setpoints (Sheet 12 of 12)