4.6 Recovery Process
In case of an incomplete booting process, the battery LED is permanently solid green. The
integrated recovery process could help.
With this recovery process, also the firmware is set back to a pre-defined beta-ver-
sion. Upgrade the firmware afterwards again to the latest instrument firmware ver-
sion. Otherwise the antenna cannot be used!
Action Result
1. Press and hold the Power button. Battery LED flashes once
and is solid green after-
wards.
2. Release Power button after about 8 s.
Instrument is ready to start the recovery.
All LEDs flashing fast.
3. Press and hold Power button until LED flashing stops.
Approximately 3 s. Release Power button.
Battery LED is solid green.
4. After about 15 s, the recovery process starts automat-
ically.
All LEDs flashing.
5. After about 2 min, the instrument switches off auto-
matically.
All LED off.
6. After about 15 s, the instrument boots up again auto-
matically.
Battery LED is solid green.
7. After about 30 s, the booting process finishes. The
instrument is ready again.
Battery LED and RTK LED
are solid green.
8. Use the WebManager to perform a factory reset. The factory reset ensures
reading out current val-
ues.
9. Check instrument firmware. Upgrade to the latest one.
Recovery process,
stepbystep
29
Operation

Other manuals for GeoMax Zenith60 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GeoMax Zenith60 Series and is the answer not in the manual?

GeoMax Zenith60 Series Specifications

General IconGeneral
BrandGeoMax
ModelZenith60 Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals