9 Verifying the installation
Table9-1 Post-installation checklist
Installation site
• No condensation on the surface of the device or inside of the device.
• Keep the device clean and dust-free.
• No packing boxes, packing bags or other packing materials left in the installation
site.
• Keep the air inlet and outlet vents of the device free of obstruction.
Device
• All modules are installed correctly.
• No slot is empty. Each is installed with a module or filler panel,
• Fan trays are installed correctly.
Cables
• The device is grounded reliably with the provided grounding cable. Both ends of
the grounding cable are securely connected.
• No switch or fuse is installed on the grounding cable.
• The power cords are connected reliably and no short circuit has occurred in
power input and output.
• Power cords, grounding cables and fiber cables are routed and bound separately.
• The cables are bound neatly with cable ties at an even distance.
• The cable labels are correct, clear, and affixed to the cable in the same direction.
Electricity safety A circuit breaker is provided for each power input line.