EasyManua.ls Logo

Hidral PH-300 - Page 22

Default Icon
44 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
IM-560en
Vers. 05
Page 20
ASSEMBLY INSTRUCTIONS
VERTICAL LIFTING PLATFORM PH-300
8 Connect the button shell and let it rest loosely on top of the vertical structure.
9 Open the shut off valve in the machine and connect the main switch (IP) to give
supply to the lifting platform.
OFF
IP switch
10 Loosen the cylinder purge bolts and actuate the ascent push button several times
until the cylinder is fully recharged and air ceases to ow from the purging holes. 
Tighten the purging bolts.
Purge outlet
Purge bolt
Purge outlet
11 Actuate the ascent push button to lift the vertical structure aproximately 300 mm
from the oor.
12 Remove the support foots from the vertical structure.
13 Position the oor on the ground, chocked about 20 mm above the lower level (with 
polystyrene, wood, etc.), below the guide and centred with it.