8 Connect the button shell and let it rest loosely on top of the vertical structure.
9 Open the shut off valve in the machine and connect the main switch (IP) to give
supply to the lifting platform.
10 Loosen the cylinder purge bolts and actuate the ascent push button several times
until the cylinder is fully recharged and air ceases to ow from the purging holes.
Tighten the purging bolts.
Purge outlet
Purge bolt
Purge outlet
11 Actuate the ascent push button to lift the vertical structure aproximately 300 mm
from the oor.
12 Remove the support foots from the vertical structure.
13 Position the oor on the ground, chocked about 20 mm above the lower level (with
polystyrene, wood, etc.), below the guide and centred with it.