8.Test Run
Only after all the checking points have been checked the unit can be operated.
(A) Check and make sure that the resistance of the terminal to ground is more than 2 MΩ, otherwise, you
cannot operate the unit before the electricity leakage point is found and repaired.
(B) Check and make sure that the stop valve has been opened before operating the unit.
(C)Make sure that turn on electric power 6 hours before operating the unit.
Make sure the power and unit run well then plug in.
Turn on the appliance and adjust it to Cooling or Heating mode according to the room temperature. Set
tem. at 16when cooling mode and 30when heating mode. Check if the appliance can run well.
Installation of the appliance is generally finished after the above operations are done. If you still have any
trouble, please contact local technical service center of our company for further information.
Pay attention to the following items while the system is running.
(A) Do not touch any of the parts by hand at the discharge gas side, since the compressor
chamber and the pipes at the discharge side are heated higher than 90℃.
( B) Use remote controller to operate ,and check whether room temperature and function well.
After testturn off the electric power.