Checking the unit with the drain-up mechanism and the oat switch
1 Turn the power supply on.
2 Pour approximately 1.8 litres of water into the drain pan. Then, the oat switch will be activated. Next, the drain pump
will start working automatically.
3 Make sure that the water ows smoothly and that no water leakage occurs. If you cannot nd water at the end of the
drain pipe, pour again approximately 1.8 litres of water into the drain pan.
4 Turn the power supply off.
N O T E
Pay attention to the insulation material thickness when the left-side piping is installed. If the insulation material is
too thick, you will not be able to install the piping in the unit.