38
PMEN0654 rev.0 - 12/2023
8
MAIN CONCERNS FOR COMMISSIONING
COMMISSIONING
8.1 Main concerns for commissioning
When installaon is completed, perform test run according to the following procedure, and hand
over the system to the customer. Perform test run regarding indoor units one by one in order, and
conrm that the electrical wiring and the refrigerant piping are correctly connected.
! CAUTION
Do not operate the system unl all the check points have been cleared:
Check to ensure that the electrical resistance is more than 1 MΩ, by measuring the resistance
between ground and the terminal of the electrical parts. If not, do not operate the system unl
the electrical leakage is found and repaired. Do not impress the voltage on the terminals for
transmission 1 and 2.
Check to ensure that the stop valves of the outdoor unit are fully opened, and then start the
system.
Check to ensure that the switch on the main power source has been ON for more than 12 hours,
to warm the compressor oil by the oil heater.
Pay aenon to the following items while the system is running:
Do not touch any of the parts by hand at the discharge gas side, since the compressor chamber
and the pipes at the discharge side are heated higher than 90°C.
DO NOT PUSH THE BUTTON OF THE MAGNETIC SWITCH(ES), it will cause a serious accident.
Do not touch any electrical components for more than three minutes aer turning OFF the main
switch.
Conrm that the gas line stop valve and the liquid line stop valve are fully open.
Conrm that the leakage of the refrigerant does not exist. The are nuts are somemes
loosened by vibraon during transportaon.
Check that the refrigerant piping and the electrical wiring conform to the same system.
Conrm that the DIP switch seng on the printed circuit board of the indoor units and the
outdoor units are correct.
Check whether or not the electrical wiring of the indoor units and the outdoor units are
connected as shown in the chapter “DIP switches”.
! CAUTION
Conrm that eld-supplied electrical components (main switch fuse, fuse-free breaker, earth
leakage breakers, wires, conduit connectors and wire terminals) have been properly selected
according to the electrical data given in the Technical Catalog of the unit and ensure that the
components comply with naonal and local codes.
NOTE
For 2 indoor units system check the indoor unit outlet air temperature at test run. If the
temperature dierence is large, approximately: 10 deg. or more (in cooling mode); 20 deg. or
more (in heang mode), recheck the refrigerant piping, installaon may have some problem.

Table of Contents

Other manuals for Hitachi UTOPIA R32 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Hitachi UTOPIA R32 Series and is the answer not in the manual?

Hitachi UTOPIA R32 Series Specifications

General IconGeneral
BrandHitachi
ModelUTOPIA R32 Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals