Transport,installationandstart‐up
UsermanualforHONR100gaspressureregulatorwithHONP095NGpilot 37
Thetestconfigurationisasfollows(conceptsketch):
Thenumbershavethefollowingmeaning:
No. Meaning
1 Inletchamber
2 Outletchamber
3
Inletstopvalvearmature
4
Gaspressureregulator
5 Blowdownlineshut‐offdevice
6 Outletstopvalvearmature
Proceedasfollows:
Step Description
1 Slowlyclosetheoutletstopvalvearmature.
2 Applythetestmediumtoalldetachablepipejoints.
3 Observethetestmediumonalldetachablepipejointsforseveralminutes.
If… then…
nofoamorbubblesareformed,
thesystemisleak‐proof.
thesystemmaybeputintooperation.
Foamorbubblesareformed,
theaffectedpipejointisleaking.
thesystemmaynotbeputintooperation.
Proceedwithstep4.
Step Description
4 Slowlyclosetheinletstopvalvearmature.
5 Depressurizetheinletchamberandtheoutletchamber.
6 Sealtheleakingpipejoints.
7 Repeattheleakteststartingwithstep1.
Testconfiguration
Checkingthesystemfor
leaks