Hardware options installation 68
For this cabling scenario, the "2LFF" labeled connector is not used.
c. Coil the excess cable to minimize the impact to airflow.
15. Install the fan cage.
16. Install the air baffle.
17. Install the access panel.
18. Do one of the following:
o Close or install the tower bezel, as needed.
o Slide the server back into the rack.
CAUTION: To prevent improper cooling and thermal damage, do not operate the server unless
all bays are populated with either a component or a blank.
19. Install the hard drives and hard drive blanks.
20. Power up the server (on page 22).
Removable media device options
The server supports the installation of up to two half-height devices or one full-height device in the
removable media bays.
Installing a half-height media device
1. Power down the server (on page 22).
2. Do one of the following:
o Open or remove the tower bezel, as needed ("Open or remove the tower bezel" on page 22).
o Extend the server from the rack (on page 24).
3. Remove the access panel (on page 25).
4. Remove the air baffle (on page 26).
5. Remove the fan cage (on page 26).