11. If you are installing the second 8 SFF hot-plug drive cage option, repeat steps 10 and 11 on the Box 2.
12. Connect all following drive cables:
SFF hot-plug drive controller cables
Drive power cable
13. Make sure that all the system cables that are routed through the front cable channel are properly secured in the metal cable tabs and
cable clamps.
14. Install the system air baffle .
15. Install the access panel .
16. Do one of the following:
Orient the server back to tower mode.
Install the server into the rack.
17. Install the SFF hot-plug drive .
18. Install the front bezel .
19. Connect the power cords:
a. Connect each power cord to the server.
b. Connect each power cord to the power source.
20. Power up the server.