7 Power-On and Commissioning
The Smart PCS can be commissioned on the SmartLogger WebUI or SUN2000
app. The SmartLogger can manage multiple devices. For details, see the
SmartLogger3000 User Manual. The app is used for local commissioning,
mainly to modify the parameters and upgrade the software version of a single
Smart PCS.
Perform deployment commissioning for the Smart PCS and ESS together. For
details, see the LUNA2000-2.0MWH Series Smart String ESS User Manual.
7.1 Powering on the Smart PCS
Precautions
Ensure that all the items in 6 Checking Before Power-On are checked and meet
the requirements before power-on.
D ANGER
Wear personal protective equipment and use dedicated insulated tools to avoid
electric shocks or short circuits.
NO TICE
Before turning on the AC switch between the Smart PCS and the power grid,
check whether the AC voltage is within the allowed range using a multimeter.
(See the local power grid standard.)
Before the equipment is put into operation for the rst time, ensure that the
parameters are set correctly by professional personnel. Incorrect parameter
settings may result in noncompliance with local grid connection requirements
and aect the normal operations of the equipment.
If the Smart PCS has not been used for six months or longer after being
installed, it must be checked and tested by professionals before operation.