Figure 5-10 Installing the short copper bar
Step 9 Remove the insulation tape from the at cables and install the at cables to the
management module.
Figure 5-11 Installing the
at cables
Step 10 Install the front panel. Use an M4 Phillips insulated torque screwdriver with a
torque of 0.6 N·m.
Step 11 Install copper bars and cables for the battery pack.
Figure 5-12 Installing copper bars and cables for the battery pack
LUNA2000-200KWH-2H1 Smart String ESS
Maintenance Manual 5 Replacing a Battery Management Module
Issue 02 (2023-02-28) Copyright © Huawei Digital Power Technologies Co., Ltd. 82