PowerCube 1000 (STC, Saudi Arabia, ICC800-A1-
C2, ESC800-A1)
Installation Guide
Issue 02
Date 2021-09-28
HUAWEI TECHNOLOGIES CO., LTD.

Table of Contents

Question and Answer IconNeed help?

Do you have a question about the Huawei PowerCube 1000 and is the answer not in the manual?

Huawei PowerCube 1000 Specifications

General IconGeneral
BrandHuawei
ModelPowerCube 1000
CategoryStorage
LanguageEnglish

Summary

About This Document

Purpose

Describes how to install the cabinet, boards, modules, and cables.

Intended Audience

Lists the target audience for this document.

Symbol Conventions

Defines the symbols used in the document.

Safety Precautions

General Safety

Provides general safety instructions for installation and operation.

Personnel Requirements

Specifies the qualifications and training required for personnel.

Electrical Safety

Details safety procedures related to grounding and AC/DC power.

Installation Environment Requirements

Defines the required environmental conditions for installation.

Mechanical Safety

Covers safety precautions for mechanical operations like hoisting.

Battery Safety

Outlines safety measures for handling and installing batteries.

PV Module Safety

Provides safety guidelines for photovoltaic modules.

DG Safety

Details safety precautions for diesel generators (DG).

Solution Scenarios

Component Descriptions

PV Module Support

Describes available angles for PV module supports.

445 W PV Module (52240257)

Details the technical specifications of the 445 W PV module.

SJB-0601A

Describes the SJB-0601A component and its specifications.

ICC800-A1-C2

Details the exterior and interior of the ICC800-A1-C2 cabinet.

ESC800-A1

Describes the exterior of the ESC800-A1 component.

ETP48600-C5B1

Details the interior and technical specifications of ETP48600-C5B1.

DC Output Box

Describes the DC output box and its PDU specifications.

Lithium Battery Bus Bar Box DCDB48-650-13B

Details the Lithium Battery Bus Bar Box and its specifications.

Junction Box for Lithium Batteries

Describes the appearance and function of the junction box.

AC Input Module AIU03-100C

Details the exterior and technical specifications of the AC Input Module.

SMU02C

Describes the SMU02C appearance, indicators, and buttons.

User Interface Module UIM05D1

Details the UIM05D1 panel, dry contacts, and COM port definitions.

DG Expansion Module GIM

Describes the GIM module, its models, indicators, and ports.

PSU

Details the PSU appearance, function, and indicator descriptions.

SSU

Describes the SSU appearance, function, and indicator descriptions.

Power Module M48500N1

Details the M48500N1 power module's appearance and indicators.

PVDU-150A1

Describes the PVDU-150A1 exterior, interior, and technical specifications.

4G Antenna

Details the technical specifications of the 4G antenna.

Digital Temperature and Humidity Sensor

Describes the sensor appearance and DIP switch settings.

Smoke Sensor

Describes the appearance of the smoke sensor.

Water Sensor

Explains how the water sensor detects water.

ESM-48100A6

Details the ESM-48100A6 panel, ports, and indicator descriptions.

Installing PV Modules

Installation Preparations

Preparing Cables

Details cable compliance, cross-sectional area, and size references.

Preparing Tools

Lists installation tools and instruments required for the process.

Installation Space Requirements

Specifies the required installation dimensions for cabinets.

Cabinet Cable Hole Positions and Definitions

Defines the positions and types of cable holes at the cabinet bottom.

Cable Routing Requirements

Installing the Cabinet

Marking Mounting Holes

Procedure for marking mounting holes for cabinet installation.

Drilling Holes and Installing Expansion Sleeves

Steps for drilling holes and installing expansion sleeves.

Hoisting a Cabinet

Instructions for safely hoisting and installing a cabinet.

Installing a Ground Cable

Procedure for installing the cabinet ground cable.

Installing Cabinets on a Concrete Floor

Steps for securing cabinets onto a concrete floor.

(Optional) Installing Right and Left Sealing Plates

Optional steps to install right and left sealing plates.

Combining Cabinets

Procedures for combining multiple cabinets.

Installing Components

Component Installation Positions

Illustrates component installation positions within cabinets.

Installing a PSU

Step-by-step guide for installing a Power Supply Unit (PSU).

Installing a Power Module M48500N1

Procedure for installing the M48500N1 power module.

Installing a DG Expansion Module

Steps for installing a DG expansion module, including SIM card.

Installing an AC Input Module

Procedure for installing the AC input module.

Installing a PVDU-150A1

Steps for installing the PVDU-150A1 in a 19-inch rack.

Installing an SSU

Instructions for installing a Solar Supply Unit (SSU).

Installing a Digital Temperature and Humidity Sensor

Guide for installing the digital temperature and humidity sensor.

Installing Batteries and Cables

Installing Lithium Batteries

Steps for securing and grounding lithium batteries.

Installing Battery Cables

Procedure for installing battery power cables.

Installing Battery Cables Between the Battery Cabinet and the ICC Cabinet

Instructions for connecting battery cables between cabinets.

Installing Cables

Installing a Dry Contact Signal Cable

Steps for connecting a dry contact signal cable.

Installing Communications Cable

Covers IP, Wireless, and BBU in-band networking.

Installing Cables for the PVDU-150A1

Procedure for connecting PVDU-150A1 cables.

Installing CAN Communications Cables

Details the installation of CAN communication cables.

Installing Cables Between the ESC800 and the ICC800

Instructions for connecting cables between ESC800 and ICC800.

Installing Cables for a Reused DG

Procedure for connecting signal and power cables for a reused DG.

Installing DC Output Power Cables for the ETP48600-C5B1

Steps for installing DC output power cables for ETP48600-C5B1.

Installing AC Input Power Cables for the ETP48600-C5B1

Steps for installing AC input power cables for ETP48600-C5B1.

Installation Verification

Cabinet Installation Checklist

Checklist for verifying cabinet installation status.

Environment Checklist

Checklist for verifying the installation environment.

Electrical Connection Checklist

Checklist for verifying electrical connections.

Cable Checklist

Checklist for verifying cable installation and routing.

Power-on and Commissioning

Connecting the Reused DG Supply

Procedure for connecting the reused DG supply.

Setting Parameters

Configuration of various system parameters.

Starting the DG Self-Check

Procedure for starting and verifying the DG self-check.

Connecting the PV Supply

Steps for connecting the PV supply under normal sunlight.

Connecting the Lithium Battery Supply

Procedure for connecting the lithium battery supply.

Connecting the Load Supply

Steps for connecting the load supply and observing system status.

Checking Before Leaving the Site

Installing Front and Rear Sealing Plates

Optional steps to install sealing plates on the cabinet base.

Installing Front and Rear Sealing Plates for Combined Cabinets

Procedure for installing sealing plates on combined cabinets.

Subsequent Operations

Final checks, sealing holes, and locking the cabinet.

Appendix

Operating Environment Classification

Classifies environments based on atmospheric corrosion levels.

UIM Dry Contacts and Alarms Associations

Maps UIM dry contacts to associated alarms.

Preparing Terminals

Describes how to cut cables and install terminals.

Installing Floating Nuts

Procedures for installing floating nuts for components.

Acronyms and Abbreviations

Related product manuals