10.7 Installing DC Output Power Cables for the
ETP48600-C5B1
Prerequisites
Switch o all load circuit breakers before installing the power cables.
Procedure
Step 1 Install DC output power cables.
Figure 10-16 Installing DC output power cables
(1) DC load
Connect DC power cables to the circuit breaker that controls LLVD based on the load
importance and capacity. The preceding gure is for reference only.
----End
PowerCube 1000 (STC, Saudi Arabia, ICC800-A1-C2,
ESC800-A1)
Installation Guide 10 Installing Cables
Issue 02 (2021-09-28) Copyright © Huawei Technologies Co., Ltd. 117