11 Installation Verication
After installing the cabinet and all equipment, check the installation items,
installation environment, and cables.
Checking the Cabinet Installation
Table 11-1 Cabinet installation checklist
No.
Check That Result
1 The cabinet is placed in accordance with the design
drawing.
□ Yes □ No
2 The base is secured. □ Yes □ No
3 All bolts, especially the bolts used for electrical
connections, are fully tightened. Flat washers and
spring washers are all installed in correct sequence.
□ Yes □ No
4 The cabinet is clean, free of dust and dirt. □ Yes □ No
5 All labels are correct, clear, and complete. □ Yes □ No
Checking the Environment
Table 11-2 Environment checklist
No.
Check That Result
1 There are no unnecessary adhesive tape or cable
ties on cables.
□ Yes □ No
2 There are no adhesive tapes, cable ties, paper
scraps, or packing materials around the cabinet.
□ Yes □ No