7.4 Installing Cabinets on a Concrete Floor
Procedure
Step 1 Place the cabinet onto the concrete
oor and align the mounting holes in the
cabinet with those in the concrete oor.
Step 2 Place at washers, spring washers, and expansion bolts into the cabinet mounting
holes.
Step 3 Level the cabinet by using leveling spacers.
Step 4 Tighten the expansion bolts to secure the cabinet.
Figure 7-10 Securing a cabinet
(1) Leveling spacer
----End
7.5 (Optional) Installing Right and Left Sealing Plates
Prerequisites
If sealing plates are required, perform the following steps to install them.
Procedure
Step 1 Install sealing plates on the left and right of a cabinet.
PowerCube 1000 (STC, Saudi Arabia, ICC800-A1-C2,
ESC800-A1)
Installation Guide 7 Installing the Cabinet
Issue 02 (2021-09-28) Copyright © Huawei Technologies Co., Ltd. 77