Figure 10-3 Installing an antenna
NO TICE
Before installing the antenna, remove the plastic shell from the antenna base to
ensure magnetic adherence.
----End
10.2.3 BBU In-band Networking
Prerequisites
The SMU connects to the baseband unit (BBU) of the base transceiver station
(BTS) for in-band communication. The BTS is required to be later than GBSS12.0
and support in-band networking.
Procedure
Step 1 Install a communications cable.
1. Connect one end of a cable to the RS485/RS232 port on the SMU.
2. Connect the other end to the MON1 or MON0 port on the BBU.
PowerCube 1000 (STC, Saudi Arabia, ICC800-A1-C2,
ESC800-A1)
Installation Guide 10 Installing Cables
Issue 02 (2021-09-28) Copyright © Huawei Technologies Co., Ltd. 107

Table of Contents

Related product manuals