NO TE
One ends of the battery rack general output power cable and black start cable are
preinstalled before delivery.
There are four types of copper bars delivered with the product: A, B, C, and D.
Copper bar D must be installed before copper bar B.
There are two types of M10 nuts for securing copper bars. Select a 15 mm or 16 mm
socket based on the site requirements.
When installing a nut, manually insert the nut into the screw plate, and then use a
socket wrench to completely secure the nut in place. This prevents the screw thread
from being stuck or stripped due to the deviation of the nut position.
Figure 8-2 Installing copper bars and cables
Step 2 Connect 48 V cables to the battery packs.
LUNA2000-200KWH-2H1 Smart String ESS
User Manual 8 Installing Cables
Issue 03 (2023-03-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 103