Figure 7-12 Installing the rack mounted re extinguishing system
7.4.2 Installing Battery Packs
Context
● You are advised to use a forklift and battery installation tray kit (installation
kit for short) to install battery packs. The installation kit is not delivered with
the product and needs to be purchased separately from the Company.
● The appearance of the battery pack installation kit in this document is for
reference only.
● Ensure that the power circuit breaker is OFF before installing batteries.
● When installing batteries, do not place installation tools, metal parts, or
sundries on the batteries. After the installation is complete, clean up the
objects on the batteries and the surrounding area.
● When moving batteries, do not remove protective components such as
protective covers or waterproof caps from battery terminals.
● Do not move or operate under the forklift tynes.
● You can operate the battery pack installation kit only after the forklift
stops moving.
LUNA2000-200KWH-2H1 Smart String ESS
User Manual 7 Installation
Issue 03 (2023-03-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 85