5.2 Clearance Requirements
The following gure shows the minimum clearance requirements for installation
and O&M. The equipment clearances must also meet the site selection
requirements (see 5.1 Site Selection Requirements).
Figure 5-1 Clearance requirements
5.3 Foundation Requirements
Figure 5-2 Foundation requirements
Requirements for foundation design solution:
● The ESS must be installed on concrete or other non-combustible surfaces.
Ensure that the installation surface is horizontal, secure,
at, and has
sucient load-bearing capacity. Subsidence or slope is not allowed.
LUNA2000-200KWH-2H1 Smart String ESS
User Manual 5 Site Requirements
Issue 03 (2023-03-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 69