6 Check Before Power-On
Check the items listed in the following table. In case of any nonconforming items,
rectify the fault and reinstall the parts. Then, check the items listed in the
following table again until all the items pass the check.
Table 6-1 Checklist
Check
Item
Acceptance Criteria
Installati
on checks
The Smart PCS is not deformed or damaged.
The Smart PCS is installed properly.
The clearance around the Smart PCS meets requirements.
Electrical
connectio
n checks
The external switches on the AC and DC sides are in the OFF
position.
All cables are intact and free from any damage or cracks.
All ground cables are connected securely and reliably.
All AC power cables are connected correctly and securely in the
correct phase sequence, and no open circuits or short circuits occur.
All DC power cables are connected securely in correct polarity, and
no open circuits or short circuits occur.
The communications cables are connected correctly and securely.
Other
check
items
The crimping module is installed securely.
The AC maintenance compartment is clean and tidy.
The DC maintenance compartment is clean and tidy.
The AC maintenance compartment door is closed and the screws on
the door are tightened.
The DC maintenance compartment door is closed and the screws on
the door are tightened.