7 Power-On and Commissioning
7.1 Powering On the Smart PCS
Prerequisites
Ensure that all the items in 6 Check Before Power-On are checked and meet
the requirements before power-on.
Precautions
D ANGER
Wear personal protective equipment and use dedicated insulated tools to avoid
electric shocks or short circuits.
NO TICE
Before turning on the AC switch between the Smart PCS and the power grid,
check whether the AC voltage is within the allowed range using a multimeter.
(See the local power grid standard.)
Before the equipment is put into operation for the rst time, ensure that the
parameters are set correctly by professional personnel. Incorrect parameter
settings may result in noncompliance with local grid connection requirements
and aect the normal operations of the equipment.
If the Smart PCS has not been used for six months or longer after being
installed, it must be checked and tested by professionals before operation.
Procedure
Step 1 Turn on the AC switch between the AC side of the Smart PCS and the transformer
station.
LUNA2000-213KTL-H0 Smart Power Control System
User Manual 7 Power-On and Commissioning