● FusionSolar app: The app is used for local commissioning, mainly to modify
the parameters and upgrade the software version of a single Smart PCS. For
details, see the FusionSolar App and SUN2000 App Device Commissioning
Guide.
For details about how to set the hot standby mode during Smart PCS
commissioning, see 7.3 Setting the Hot Standby Mode.
7.3 Setting the Hot Standby Mode
Context
The hot standby mode applies to only on-grid scenarios and does not apply to o-
grid and on/o-grid scenarios.
Procedure
Step 1 Log in to the SmartLogger WebUI.
Step 2 Choose Deployment Wizard > Connect Device , and click Next.
Step 3 On The subarray hot standby mode, set the hot standby mode parameter as
required and click Settings.
Figure 7-1 Setting the hot standby mode
LUNA2000-213KTL-H0 Smart Power Control System
User Manual 7 Power-On and Commissioning
Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd. 76