6 System Commissioning
6.1 Verication Before Power-On
Table 6-1 Check items and acceptance criteria
No. Check Item Acceptance Criteria
1 SUN2000 The SUN2000 is installed correctly and
securely.
2 WLAN antenna The WLAN antenna is installed
correctly and securely.
3 Cables routing Cables are routed properly as required
by the customer.
4 Cable tie Cable ties are evenly distributed and no
burr exists.
5 Grounding The PE cable is connected correctly,
securely, and reliably.
6 Switch The DC switch and all the switches
connecting to the SUN2000 are OFF.
7 Cable connection The AC output power cable, DC input
power cable, battery cable, and signal
cable are connected correctly, securely,
and reliably.
8 Unused terminal and port Unused terminals and ports are locked
by watertight caps.
9 Installation environment The installation space is proper, and
the installation environment is clean
and tidy.
SUN2000-(2KTL-6KTL)-L1
User Manual 6 System Commissioning
Issue 04 (2021-04-01) Copyright © Huawei Technologies Co., Ltd. 58