24
Setting the Program Cycle Start Time(s)
Each Program can have three separate start times. For mature
landscapes, one start time per Program is generally sufficient. When
establishing a new lawn, using two or three start times with short valve
run times can provide the additional irrigation required for grow-in, at a
reduced rate to help prevent runoff and erosion.
1. Place the Function switch in the Set Programs position.
2. Select Program A, B or C.
3. Turn the Dial to select Start Time 1 (2 or 3).
4. Press the or button to set the start time (note AM/PM).
Note: To remove a start time, select Off, displayed between 11:59–
12:00 and 5:59–6:00 (AM and PM).
5. Repeat steps 3 and 4 to set additional start times for this Program.
6. Repeat steps 2–5 for each Program as needed.
7. When finished, return the Dial to the Current Time position.
8. Return the Function switch to the Run position.
Setting the Program Watering Day Schedule
Watering days can be scheduled for each Program using one of the
following methods:
• Weekdays - Schedules watering for specific days of the week.
• Skip Day - Schedules watering days by interval frequency; e.g.,
every day (01), every-other-day (02) etc.
• Odd/Even Date - Schedules watering days based on Odd- or Even-
numbered calender days.
To set a Weekdays Schedule:
1. Place the Function switch in the Set Programs position.
2. Select Program A, B or C.
3. Turn the Dial to the desired weekday position.
4. Press the button to select the day (On), or the button
remove the day (Off) from the watering day schedule.
5. Repeat steps 3 and 4 to schedule additional weekdays as needed.
6. Repeat steps 2–5 for each Program as needed.
7. When finished, return the Dial to the Current Time position.