LEVELUPS SERİSİ 10-20 KVA OPERATION
AG-SD-83 / Publication Date: 15.09.2014 / Rev. No: 0 / Rev. Date:
3.1.2 Pre-installation check up
Before installation of the device the following control actions must be taken, these first and most
important steps will secure the accurate operation of the product.
Check if any damage was done to the device during transportation. Report any damages
instantly.
Make sure that model power rating is right. Check the device label for the actual power
rating.
3.1.3 Positioning
The device and the batteries are designed for the indoor use. Keep the device in a cool and dry
place, with the air flow, humidity and temperature values must be within the specified range.
3.1.3.1 Positioning The UPS
In the LevelUps 10- 20 KVA Series, fresh air enters the device from the front and goes out from
the fans on the rear side of the device. Care must be taken in order not to cover the air entrance
and exit spots. UPS must be positioned on a place where it is protected from water etc. contact
risks.
If the area is dusty, optional filters must be used for such environment. These filters usage must
be done as per instructions document.
Below given cooling values must be provided to reach the maximum level of performance of UPS
and batteries
UPS
Amount of BTU /h
for cooling
Bridge Load 100% (Non-lineer)
estimated BTU / h value for load
working
10KVA
1,800
2,100
15KVA
2,600
3,100
20KVA
3,500
4,100