11-2
11.2 Maintenance Plan
The following tasks must be conducted by professional maintenance personnel
approved by the company. Please contact the company if the following
maintenances are needed. Must clean and disinfect the device before the test or
maintenance.
Inspection/Maintenance Items
Perform a safety inspection according
to the IEC60601-1 standard.
Once every two years. Perform after the
board is changed or the syringe pump is
accidentally dropped.
Preventive maintenance (refers to the
Maintenance Manual for pressure
calibration, sensor calibration, and
pump inspection).
Once every two years, or when you
suspect the occlusion alarm is abnormal,
the flow volume is inaccurate, or the
syringe is incorrectly identified.
11.3 View Information
Select [Main Menu]→[History Record]. In the [History Record] interface, you can
view the infusion parameters, alarm information, operation information and other
information.
Select [Main Menu]→[System Options]→[Version Information]. In the [Version
Information] interface, you can view the Software Version, Brand Library Version
and other versions.
11.4 Accuracy Calibration
The syringe in the syringe pump needs no daily calibration. But calibration is
required when the syringe pump is used for the first time, is replaced with a new
syringe brand or when you suspect the deviation of the flow volume is much larger.
Prepare the following materials before the calibration:
Syringe: Standard 5ml, 10ml, 20ml, 30ml, and 50ml/60ml syringes, without
liquid.
The steps for calibration are as follows:
1. Load the syringe correctly and pull the syringe to the full scale position. "L" in
the fig. below refers to the full scale position of the 50ml syringe.
2. Select [Main Menu]→[User Maintenance]→Input User Maintenance
Password→[System Calibration]→[Accuracy Calib.].
3. Select Brand and Size of the current syringe in the [Syringe Selection]
interface.