8.6 Project planning of the Fast Start Up
Topology To configure the module for the Fast Start-Up (FSU) and to achieve the de-
sired run-time characteristics, several steps are needed. The corresponding
parameters are set directly in the module.
Select the module in the Topology view.
Fig. 8-37: Topology
Activation of the priori-
tized startup
Fig. 8-38: Enabling prioritized startup
Activate the menu option Prioritized startup.
This activates the fundamental FSU functionality for the module.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Murr Elektronik MVK-MPNIO Series and is the answer not in the manual?

Murr Elektronik MVK-MPNIO Series Specifications

General IconGeneral
BrandMurr Elektronik
ModelMVK-MPNIO Series
CategoryControl Unit
LanguageEnglish

Related product manuals