REASSEMBLY OF THE HAMMER
18. Install the tool and retaining pin.
19. Charge with nitrogen gas and inspect
for gas leaks.
a. Charge nitrogen gas to the
specified gas pressure. See
“Gas Charging the Hammer”
pages 29 through 32.
b. Check for gas leaks. See “Gas
Leakage” page 27.
20. Grease the tie rods (GH6 ONLY).
a. After the tie rods have been
torqued, install grease fittings
(30) as shown. Grease until no
more grease is accepted.
Remove the grease fittings and
install the existing plugs (TT).
21. Install the hammer into the hammer
bracket.